Library Building Project
Timeline
| May 2008 – June 2008 | Demolish Franciscan building |
| June 2008 – August 2008 | Construction of two temporary Library Annexes at Lakeview site |
| August 2008 – Sept. 2008 | Relocation of Library, AT and CTFD Services to other campus locations |
| October 2008 | Existing Library building closed |
| June 2008 – October 2009 | Construction of Western Addition (LRS + 2 Floors) |
| May 2009 – July 2011 | Construction of North Addition and Renovation of Existing Building |
| Fall 2011 | New Leonard & Sutro Library Building Opens |